Lag is a delay between two tasks that have a dependency.

The following illustration shows a 2 day lag between two tasks having Finish-to-Start dependency:

The following illustration shows a -2 days lag (negative) between two tasks having Finish-to-Start dependency:

Lag value can be specified in percentage (lead time), such as 50%. This means setting the lage to be equal to half of the predecessor’s duration.